SARATOGA RACINO BUILDING RENOVATION & EXPANSION

Owner: Saratoga Gaming & Raceway
Site: Saratoga Springs, NY
Value: $2,000,000
Project Objectives:
Fast-track subcontract services for Perini Building Co., Inc. & L.P. Ciminelli in Fall/Winter 2003 & 2006, respectively.
 
Scope of Work:
  • Clearing/grubbing and earthwork for parking lot expansion and internal roads.
  • Miscellaneous excavation, utility relocations and abandonment, selective demolition, backfill and installation of gravel/crushed stone for footings and grade beams for addition to the existing facility.
  • Trenching and concrete ductbanks provided for over 2,500-feet of conduit installation.
  • Overlay of the existing parking area, layout and construction of new sidewalks and granite curbing, as well as installation of a new storm sewer system.
  • Interior and exterior concrete foundation and flatwork construction for ~30,000 square foot building addition. 
  • Temporary enclosure provided and maintained for cold weather concrete work within building addition.
 