Scope of Work:
· Phased excavation of approximately 10,000 cubic yards, up to 12-feet deep.
· Temporary water collection system installed and maintained to collect adjacent building rain water from existing roof drains.
· Furnished and installed over 1,000-feet of storm pipe and drainage structures, as well as a permanent pump station.
· Installation of over 400 auger-cast piles approximately 55-feet in depth were completed in less than one month, with a fixed mast drill rig and crane with flying leads.
· 3,000-square feet of concrete and soil-mixed wall was installed where sloping/benching was not possible.
· Eliminated the need for an extensive well point dewatering systems by devising a way to sequence foundation excavation and underdrain installation, thus saving the Owner over $160,000.
|
|||||||||||